Armada Township moratorium
Armada Township, Michigan paused new data center approvals on 14 Jan 2026 for 6 months, citing specific project. Checked 23 Nov 2026
In force since 14 Jan 2026No end date on record
The facts
- Applies to
- Not specified
- Reason
- Recent growth in the building of data centers in the region; the Board sought time for Planning Commission review, resident input, and legal analysis of appropriate zoning standards
- Term
- 180 days from January 14, 2026 (Resolution No. 2026-02); extended an additional 180 days from June 10, 2026 by Resolution No. 2026-10
- Legal basis
- Resolution No. 2026-02 (adopted January 14, 2026, unanimous 5-0), extended by Resolution No. 2026-10 (adopted June 10, 2026)
- What happened next
- Pending; Township Board, staff, and legal counsel continuing to study data center regulations during the extended moratorium period
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Armada Township votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.