Barnes County moratorium
Barnes County, North Dakota paused new data center approvals on 19 May 2026, citing zoning and rules and specific project. Checked 23 Nov 2026
In force since 19 May 2026No end date on record
The facts
- Passed by
- Barnes County Commission, 19 May 2026
- Applies to
- None formally pending; rumored project in southern Barnes County cited as the impetus.
- Reason
- Preemptive: no data center project was formally pending, but the board acted on rumor of a possible project in southern Barnes County to allow time to draft zoning/ordinance regulations before any application could be filed. Several citizens asked the board to extend the pause to a full year, but the motion that passed and was recorded was for six months.
- Term
- Six months; the May 19, 2026 minutes do not specify an effective date or exact expiration.
- Legal basis
- Barnes County Commission motion adopting a six-month moratorium on new data center building permits/applications countywide, per official commission minutes; no separately numbered resolution/ordinance was cited in the minutes.
- What happened next
- Commission minutes record unanimous approval of a six-month data-center moratorium on May 19, 2026; the effective date is not specified in those minutes. The earlier row described countywide new building permits and applications; that detail is not independently established by these minutes.
Campuses in reach
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Barnes County votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.