Data center projects in North Dakota
2 campuses are planned or being built in North Dakota, with 9 MW disclosed so far. 1 has a site permit or later. Checked 27 Nov 2026
2Campuses
9 MWDisclosed capacity
2Moratoria in force
North DakotaOpen map
One or two campusesThree or more
Applied Digital JMS
Applied DigitalStutsmanSite permit9 MWCoal Creek Data Center
Rainbow Energy CenterMcLeanZoning
Utility, substation and records for every rowUtility and substationStart Pro · $299/mo
No campuses match
Where North Dakota stands
By stage
Top counties
- McLean1
- Stutsman1
Top owners
Applied Digital9 MW1
Rainbow Energy CenterNot on record1
Track North Dakota in the app, free
Check your email to finish
What the stages mean
- AnnouncedNamed by the owner or an official
- ZoningRezoning filed or approved
- Site permitSite plan or land use approved
- Building permitPermit to build issued
- ConstructionWork on site has started
- OperatingRunning and taking load
Questions
How many data centers are being built in North Dakota?
2 campuses are planned or being built. 0 are under construction and 1 has a site permit or later
Zoning approved 1 · Site permit 1
Which North Dakota counties have the most?
McLean 1Stutsman 1
Who is building them?
Applied Digital 1Rainbow Energy Center 1
How do you know a project is real?
Every campus here is matched to at least one public filing: an announcement, a rezoning, a site plan or a permit. As of 2026-11-27, Wattlas lists 17 campuses in North Dakota, 14 of them operating and 1 reported plans not yet confirmed by a filing