Bensalem Township moratorium
Bensalem Township, Pennsylvania paused new data center approvals on 8 Jun 2026 for 6 months, citing zoning and rules. Checked 23 Nov 2026
Started 8 Jun 20266 of 6 months passedEnds 5 Dec 2026
The facts
- Reason
- Zoning ordinance lacked provisions for data centers, solar energy, and wind energy.
- Term
- 180-day municipal curative-amendment period after declaring portions of the zoning ordinance substantively invalid as to data centers, solar energy, and wind energy. Official minutes describe the protected period as a 180-day moratorium.
- Legal basis
- Township Council resolution, Municipal Curative Amendment (Pennsylvania Municipalities Planning Code Section 609.2)
Campuses in reach
EquinixPhiladelphia CountySite permit·EquinixAmazon Falls Township Campus (PNE100)Bucks CountyConstruction·≈66–140 MWData center projectMontgomery CountyAnnounced·640 MWMCD 7, LLC Data CenterMontgomery CountyAnnounced·MCD 7Sei Global Services, IncMontgomery CountyAnnounced·Sei Global ServicesPNJ-01 / -02Middlesex CountyAnnounced·Chirisa
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Bensalem Township votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.