Blanchester moratorium

Blanchester, Ohio paused new data center approvals on 12 Mar 2026. Checked 23 Nov 2026

In force since 12 Mar 2026No end date on record

The facts

Applies to
Not specified
Term
24 months (2 years) from the effective date, per Ordinance 2026.007 Section 1
Legal basis
Ordinance 2026.007, "Ordinance Establishing Data Center Moratorium"
Reason
General council concern that the village electric grid could not support a data center's power needs, plus unresolved questions about energy sourcing raised at a council-attended data-center webinar; no specific project or applicant was pending.
What happened next
No data-center-related zoning or council action has followed the March 12, 2026 adoption; council minutes for April 9, May 14, and June 11, 2026 (the most recent available) contain no further mention of data centers or the moratorium.

Know when Blanchester votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Blanchester paused data centers?