Waynesville moratorium
Waynesville, Ohio paused new data center approvals on 4 May 2026, citing zoning and rules. It covers 1 tracked campus. Checked 23 Nov 2026
In force since 4 May 2026No end date on record
The facts
- Applies to
- None named; the administrator told a broker marketing the Lemay property about the moratorium in September 2026.
- Reason
- Allow the village to research data centers and see what the State of Ohio task force determines; review whether zoning code needs updating.
- Term
- 180 days (OCJ map: 'Council passed 180-day moratorium', expiring Oct. 31, 2026, which is exactly 180 days from the 2026-05-04 adoption); ordinance text not found
- Legal basis
- Village of Waynesville Ordinance No. 2026-020 (emergency): temporary moratorium on acceptance, processing and approval of applications for large-scale data center development; establishes Data Center Study Committee
- What happened next
- Data Center Study Committee (council members Gallagher, Powell, Colvin) to recommend zoning code updates.
Campuses in reach
CIN5 Cincinnati North Cincinnati Data CenterWarren CountySite permit·≈39–180 MWAWS Wilmington data centerClinton CountySite permit·≈370–1,700 MWEncore Technologies MSB1Montgomery CountySite permit·≈10–46 MWPrologis Butler Data CenterButler CountyZoning·250 MWCMH01 Holdings LPClark CountySite permit·150 MWConstant CompanyClark CountyAnnounced·Constant
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Waynesville votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (1 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.