In forceMoratorium

Bloomingdale moratorium

Bloomingdale, Georgia paused new data center approvals on 20 Aug 2026, citing specific project and water use. Checked 23 Nov 2026

In force since 20 Aug 2026No end date on record

The facts

Applies to
Project Camellia is reported in neighboring Effingham County; this review did not establish which projects in Bloomingdale, if any, were affected.
Reason
Reporting placed OpenAI’s Project Camellia in neighboring Effingham County in context; the city cited protection of residents’ access to power and water. A causal link to the project has not been established.
Term
August 2026 reporting describes a six-month moratorium through February 16, 2027. The proposed resolution specified 11:59 p.m. and allowed shortening or extension; the enacted terms remain unverified.
Legal basis
August 2026 reporting describes a City of Bloomingdale moratorium on applications relating to new or expanded data centers. Proposed Resolution No. 2026-012 contains related terms; the executed instrument remains unverified.
What happened next
City Council unanimously adopted a six-month data center moratorium while the city studies regulations.

Know when Bloomingdale votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Bloomingdale paused data centers?