In forceMoratorium

Savannah moratorium

Savannah, Georgia paused new data center approvals on 27 Aug 2026 for 5 months, citing specific project and zoning and rules. Checked 23 Nov 2026

Started 27 Aug 20263 of 5 months passedEnds 29 Jan 2027

The facts

Passed by
City Council, 27 Aug 2026
Applies to
None in city limits; prompted by OpenAI's Effingham County project
Term
155 days from adoption (to about 2027-01-29)
Reason
OpenAI's announced 3.2 GW 'Project Camellia' campus in neighboring Effingham County and growing interest from data center companies; need to study noise, water, neighborhood and grid impacts
Legal basis
City Council ordinance imposing a 155-day temporary moratorium on data centers of 10 MW or greater and on conversion of industrial buildings of 200,000 sq ft or more to data center use (ordinance number not published in sources reviewed)
What happened next
City Council adopted a 155-day moratorium on large-scale data center development and conversions within city limits.
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo

Know when Savannah votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Savannah paused data centers?