Broken Bow moratorium
Broken Bow, Nebraska paused new data center approvals on 14 Jul 2026, citing zoning and rules. Checked 23 Nov 2026
In force since 14 Jul 2026No end date on record
The facts
- Applies to
- None identified
- Term
- Six months, or until permanent zoning regulations take effect, whichever first
- Legal basis
- Ordinance 1314
- Reason
- No existing regulations governing data centers; city wants time to draft zoning rules
- What happened next
- The City Council passed and approved data-center zoning Ordinance 1317 on September 8, 2026. Its effective date and the resulting moratorium sunset remain unverified.
Campuses in reach
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Broken Bow votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.