MARA Kearney Facility
A 368 MW data center campus in Kearney, Nebraska, built by Mara. It was announced in March 2026 and has 1 public record behind it. Checked 27 Nov 2026
AnnouncedStage since Mar 2026
368 MWCapacity, as stated
1Public records
13Moratoria nearby
How far along
- AnnouncedMar 2026
- Zoning
- Site permit
- Building permit
- Construction
- Operating
The announced dates from March 2026. A rezoning or site permit is the next step. Kearney County has a moratorium in force 42 km away
Buffalo County, NebraskaParcel, substation and lines
The record
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
1 record
- Record 1
Utility, substation and 1 public record for MARA Kearney FacilityOpen the app, freeStart Pro · $299/mo
Opposition nearby
Kearney County moratorium42 kmIn forceBroken Bow moratorium77 kmIn forceCuster County moratorium82 kmEndedRed Willow County moratorium139 kmIn force
Opposition in NebraskaKnow when this campus moves
Check your email to finish
Questions
Who owns MARA Kearney Facility?
Mara, according to public records.
How big is it?
368 MW, as stated in a public filing.
Has it been approved?
Not yet. It was announced in March 2026.
Is there local opposition?
Yes. 10 moratoria in force and 1 pending and 2 ended nearby.