Butler County moratorium
Butler County, Ohio paused new data center approvals on 16 Jun 2026, citing land use and zoning and rules. It covers 11 tracked campuses. Checked 23 Nov 2026
In force since 16 Jun 2026No end date on record
The facts
- Passed by
- Butler County Board of Commissioners, 16 Jun 2026
- Reason
- County-initiated pause on data center applications and permits in county-zoned townships pending policy development
- Term
- Six months following the effective date under Section 1 of the reproduced resolution text. The county administrator reported June 17, 2026 effectiveness; a controlling effective-date instrument and exact endpoint remain unverified.
- Legal basis
- Butler County Board of Commissioners Resolution 26-06-00963, recorded adopted June 16, 2026; reproduced Sections 1–5 restrict data-center application/permit processing in county-zoned Hanover, Lemon, Madison, Milford, Oxford and Ross townships. A signed executed copy remains unverified.
- What happened next
- June 16 official minutes record the six-month moratorium adopted; the legislative file records Dixon moving, Carpenter seconding and Rogers, Carpenter and Dixon voting aye. Reproduced Sections 1–5 cover application and permit processing for establishment or expansion and suspend or toll specified review periods. The legislative meeting-history section also displays Draft; the linked minutes corroborate adoption. In a July 2 report, Oxford Free Press attributed June 17 effectiveness to an email from County Administrator Judi Boyko.
Campuses in reach
Prologis Butler Data CenterButler CountyZoning·250 MWKrogerHamilton CountyAnnounced·KrogerCIN5 Cincinnati North Cincinnati Data CenterWarren CountySite permit·≈39–180 MWEncore Technologies MSB1Montgomery CountySite permit·≈10–46 MWAWS Wilmington data centerClinton CountySite permit·≈370–1,700 MWJ5 Piqua Data CenterMiami CountyAnnounced·1,400 MW
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Butler County votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (11 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.