In forceMoratorium

St. Bernard moratorium

St. Bernard, Ohio paused new data center approvals on 24 Sep 2026, citing specific project and zoning and rules. Checked 23 Nov 2026

In force since 24 Sep 2026No end date on record

The facts

Applies to
CAI Investments LLC data center at the former St. Bernard Soap Company (P&G Ivorydale) building on Spring Grove Avenue; 150,000 sq ft, 24 MW.
Reason
CAI Investments proposal to convert part of the former St. Bernard Soap Company / P&G Ivorydale plant into a 150,000 sq ft, 24 MW data center; no data center regulations in the code.
Term
12 months, as reported by WVXU; the final amended text and operative interval remain unverified.
Legal basis
Ordinance 36-2026, amended and adopted 7-0 on September 24, 2026, imposing a data-center application and approval moratorium; the executed amended text and operative exceptions remain unverified.
What happened next
Council adopted the moratorium. The village said CAI’s previously filed BZA application could proceed; the zoning administrator reported on October 8 that the hearing would be postponed to December.

Know when St. Bernard votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near St. Bernard paused data centers?