Carroll County moratorium
Carroll County, Maryland paused new data center approvals on 19 Feb 2026, citing zoning and rules. Checked 23 Nov 2026
Started 19 Feb 20269 of 12 months passedEnds 19 Feb 2027
The facts
- Term
- One year from the effective date (2026-02-19) to 2027-02-19
- Applies to
- Acceptance, processing, review and approval of all plans for data processing centers as defined in Carroll County Code § 158.002.
- Reason
- Board of Commissioners voted (2026-01-16 draft-ordinance instruction) to preemptively study and regulate data centers even though no developer had yet applied for a permit in the county.
- Legal basis
- Ordinance 2026-02, codified at Carroll County Code Section 158.176 ('Data Processing Centers; Temporary Deferral')
- What happened next
- The county has not yet adopted a permitted-use table entry, district list, or dimensional standard for data processing centers separate from this deferral, which functions as a placeholder while the Commissioners work out permanent siting rules.
Campuses in reach
Aligned Frederick CampusFrederick CountySite permit·72 MWAmazon AWS BWI - Building 4Frederick CountySite permit·≈81–170 MWRowan Bauxite II - Building 3Frederick CountySite permit·Rowan Digital InfrastructureControl Data Corp.Baltimore CountySite permit·Control DataUfd Data CenterYork CountySite permit·United Fiber DataDickerson Data CenterMontgomery CountyZoning·Atmosphere Data Centers
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Carroll County votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.