Montgomery County moratorium
Montgomery County, Maryland paused new data center approvals on 28 Jul 2026, citing zoning and rules and land use. It covers 12 tracked campuses. Checked 23 Nov 2026
Started 28 Jul 20264 of 18 months passedEnds 10 Feb 2028
The facts
- Applies to
- Covered data centers have existing or projected aggregate monthly electricity demand of at least 25 MW, subject to specified exclusions. The Act applies to the specified conditional-use applications filed before or after effectiveness, pending regulatory review, or approved without an issued permit.
- Reason
- Council concern over unresolved zoning/permitting pathway for data centers following prior zoning changes; competing council proposals (6-month vs. 2-year) were reconciled into an 18-month compromise.
- Term
- 18 months from the bill's effective date (specific calendar end date not stated in the press release)
- Legal basis
- Expedited Bill 19-26 (Department of Permitting Services barred from issuing data center permits during the moratorium) paired with Zoning Text Amendment 26-01 (prohibits hyperscale data centers countywide and redefines 'data center').
- What happened next
- Council intends to use the 18-month period to develop comprehensive data-center development guidelines in coordination with state officials.
Campuses in reach
Dickerson Data CenterMontgomery CountyZoning·Atmosphere Data CentersProsperity Drive Data Center, LLCMontgomery CountySite permit·≈18–84 MWAmazon DCA-54Fairfax CountySite permit·≈4–9 MWAmazon IAD-1 IAD-9Fairfax CountySite permit·≈4–8 MWBogle Drive Data CenterFairfax CountySite permit·≈10–44 MWData center projectFairfax CountySite permit·65 MW
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Montgomery County votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (12 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.