Cass County moratorium
Cass County, Nebraska paused new data center approvals on 11 Aug 2026, citing specific project and zoning and rules. Checked 23 Nov 2026
In force since 11 Aug 2026No end date on record
The facts
- Passed by
- Board of Commissioners, 11 Aug 2026
- Applies to
- Tenaska/Google-linked data center and natural-gas power plant proposal near Murray/Beaver Lake (1,354 acres optioned as of June 2026); no formal application had been submitted as of the Aug. 11 vote, per the county zoning administrator.
- Reason
- specific_project trigger (Tenaska/Google-linked proposal: Tenaska optioned 1,354 acres in Cass County along Highway 75 south of Murray and Beaver Lake for a data center/natural-gas power plant project) combined with a regulatory gap; a separate set of proposed zoning regulations was tabled to Sept. 22, 2026 for further discussion.
- Term
- 12 months (a 'baseline' minimum per Commissioner Alexander DeGarmo, extendable if more time is needed, or endable early if regulations are adopted sooner)
- Legal basis
- Board of Commissioners resolution (specific resolution number not located in sources reviewed)
- What happened next
- A 12-month moratorium on data-center permits was reported adopted August 11, 2026; KETV reported November 3 approval of zoning Resolution 2026-11 and continuation of the moratorium at that time.
Campuses in reach
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Cass County votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.