Gage County moratorium
Gage County, Nebraska paused new data center approvals on 16 Sep 2026, citing zoning and rules and grid and power. Checked 23 Nov 2026
In force since 16 Sep 2026No end date on record
The facts
- Passed by
- Board of Supervisors, 16 Sep 2026
- Applies to
- None named; officials stated no permit application was pending. Tenaska (an Omaha-based energy developer also behind projects in Cass and Otoe counties) was referenced as active in the region.
- Reason
- County has no data-center-specific regulations; Board wanted time to develop them following a contested public process (a June 2026 Planning and Zoning Commission hearing drew 170+ people and a Sept. 3, 2026 supervisors' hearing drew 120+ people, most urging an 18-month or longer term).
- Term
- 12 months from 2026-09-16, superseding an earlier 8-month moratorium the Board had passed in August 2026; the Planning and Zoning Commission had recommended an 18-month term after a crowded June 2026 public hearing, but the Board adopted 12 months instead.
- Legal basis
- Board of Supervisors resolution (specific resolution number not located in sources reviewed)
- What happened next
- 12-month data center permit moratorium adopted to allow time to develop county-specific data center regulations; supersedes the county's prior 8-month moratorium from August 2026.
Campuses in reach
No tracked campus within 80 km
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Gage County votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.