In forceMoratorium

Champaign County moratorium

Champaign County, Illinois paused new data center approvals on 23 Apr 2026, citing zoning and rules and infrastructure. It covers 2 tracked campuses. Checked 23 Nov 2026

In force since 23 Apr 2026No end date on record

The facts

Passed by
County Board, 23 Apr 2026
Applies to
Data centers with at least 10,000 square feet of processing area. Draft zoning language also discussed "big" data centers rated at 10 MW or greater for related standards. Proposed projects would not be approved, and pending projects would be held in abeyance during the moratorium.
Reason
County materials cite groundwater quality and safety, Mahomet Aquifer and water use concerns, energy use, and need for standards for large-scale data centers before proposals arrive.
Term
12 months (Board reverted 9-month ELUC amendment back to 12 months on 2026-04-23 per WGLT and Prairie Rivers Network reporting; Board Member Emily Rodriguez introduced the amendment)
Legal basis
Zoning Case 196-AT-26, a Champaign County Zoning Ordinance text amendment (new Section 5.6, amending Section 5.2) imposing a 12-month development moratorium on data centers of at least 10,000 sq ft of processing area, recommended for enactment by the Zoning Board of Appeals 4-0 on 2026-03-19, and adopted by the County Board on 2026-04-23 as Ordinance No. 2026-9.
What happened next
Pending. The County Board created a Data Center Activities Task Force in February 2026 to recommend zoning amendments.

Know when Champaign County votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (2 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Champaign County paused data centers?