Chatham County moratorium
Chatham County, North Carolina paused new data center approvals on 11 Feb 2026, citing specific project and zoning and rules. Checked 23 Nov 2026
Started 11 Feb 20269 of 12 months passedEnds 11 Feb 2027
The facts
- Term
- 12 months, to 2027-02-11, or earlier if new zoning regulations are adopted
- Legal basis
- Ordinance 26-0061; N.C.G.S. 160D-107; hearing under N.C.G.S. 160D-601
- Applies to
- Triangle Innovation Point West; ordinance covers data centers, data processing facilities, cryptocurrency mining operations, and related uses in unincorporated Chatham County outside municipal ETJs.
- Reason
- Potential large-scale data center interest at Triangle Innovation Point West in Moncure; county findings cite water and electricity use, greenhouse gas emissions, pollution, e-waste, noise, and unaddressed zoning categories.
- What happened next
- The county adopted a twelve-month moratorium and planned zoning work. The court granted Eco TIP West summary judgment on liability and attorney fees on 2026-09-17 and reserved damages for later proceedings; the retained order does not specify which pleaded legal ground controlled.
Campuses in reach
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Chatham County votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.