City of Ames moratorium
City of Ames, Iowa paused new data center approvals on 28 Jul 2026, citing specific project and zoning and rules. It covers 1 tracked campus. Checked 23 Nov 2026
Started 28 Jul 20264 of 9 months passedEnds 1 May 2027
The facts
- Passed by
- Ames City Council, 28 Jul 2026
- Term
- About nine months, until May 1, 2027; may be lifted earlier or extended
- Applies to
- Lightedge 25 MW, 10.86-acre colocation proposal at Ames Municipal Airport (delayed; company now pursuing Boone).
- Reason
- Lightedge proposal to lease 10.86 acres of city airport land for a 25 MW colocation facility; staff memo on regulatory options.
- Legal basis
- Ames City Council Resolution 26-488, adopted 4–2 on 2026-07-28, temporarily delaying data center development in Ames.
Campuses in reach
Clop Des Moines IA, LLCPolk CountySite permit·5 MWEdged Des Moines, LLCPolk CountyConstruction·13 MWMCC Iowa, LLCPolk CountySite permit·MCC IowaMicrosoft Corporation - Willow Creek/Ginger East DataPolk CountyConstruction·MicrosoftTract AltoonaPolk CountyZoning·1,000 MWMicrosoft Corporation - Alluvium Data CenterDallas CountySite permit·≈54–250 MW
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when City of Ames votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (1 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.