EndedMoratorium

City of Aurora moratorium

City of Aurora, Illinois paused new data center approvals on 25 Sep 2025 for 6 months, citing zoning and rules and infrastructure. The pause has ended. It covers 14 tracked campuses. Checked 23 Nov 2026

Started 25 Sep 2025EndedEnded 24 Mar 2026

The facts

Term
180 days, with one-time 30-day extension invoked before final ordinance adoption
Legal basis
Ordinance O25-064
Applies to
New data center and warehouse developments, subject to carve-outs for previously filed entitlement applications, existing data center remodels, routine maintenance, and public safety facilities. Aurora reported five data centers in city limits and five more in development when it adopted the permanent rules.
Reason
Rapid expansion of data centers in northern Illinois; existing code classified data centers as warehouses; city cited neighborhood complaints, noise, emissions, high energy and water use, stormwater, utility demand, infrastructure strain, and fiscal impacts.
What happened next
City Council approved new rules on 2026-03-24, described by the city as adopted on 2026-03-25. New data centers are conditional uses requiring public hearing, public notice, City Council approval, development agreement, water study and plan, energy plan, sound study and plan, noise and vibration limits, energy and water limits, no evaporative cooling, no modular nuclear, annual energy and water reporting, annual noise testing, and either on-site renewables or battery storage or alternative compliance.

Know when City of Aurora votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (14 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near City of Aurora paused data centers?