Chicago
Chicago is market 15 of 34: about 5.3 GW across 55 campuses in 9 counties. 6 under construction and 2 moratoria in force. Checked 28 Nov 2026
Largest campuses
All 55 campuses
The shape of the market
By stage
- Announced15
- Zoning5
- Site permit21
- Building permit8
- Construction6
Stated and estimated
- Stated on record40 MW
- Our estimate≈5.3 GW
What could slow it
- Utilities serving these campuses
- Grid requests on file
- Substations, water stress and flood
- Download this market as CSV
Track Chicago in the app, free
Questions
How many data centers are in Chicago?
55 tracked pipeline campuses (5.3 GW estimated total, 40 MW reported) across 9 counties in Illinois. Key signals: 9 sites showing earthwork in satellite imagery, 3 active/extended moratoria, 55 pipeline sites in high/extremely high water stress.
Estimated pipeline MW combines reported capacity (40 MW) with estimates from floor area, acreage, investment or backup generation. 20.5% of monitored sites show clearing.
Who is building the most?
Which counties have paused new data centers?
2 moratoria are in force in Chicago, covering 4 campuses. 5 moratoria and 66 petitions are on record across the market. 55 of 55 campuses sit in high water stress.
How is this market drawn?
How large is the Chicago data center pipeline?
Wattlas tracks 55 upcoming pipeline campuses in Chicago (30 verified, 6 under construction, 29 permitted), representing 40 MW in reported capacity and 5,330 MW total estimated pipeline. Projects with the largest reported figures include Tract Morris Data Center (1,000+ MW), Data center project (1,000+ MW), Equinix LLC (500–999 MW).
What are industrial power rates and serving utilities in Chicago?
Chicago sits in PJM. Industrial power rates, serving utilities, substation and transmission distance, large-load tariffs and interconnection queue depth for every tracked site are included in Wattlas access.
What local opposition, moratoria, or water risks affect Chicago data centers?
Across tracked campuses in Chicago, Wattlas links 3 active or extended moratoria (5 total) and 66 public petitions. On physical site risk, 55 of 55 pipeline campuses sit in High or Extremely High baseline water stress (10 Extremely High). Floodplain and ozone screening are included in Wattlas access.
How many Chicago data center sites show active satellite land clearing?
Of 44 pinpointed pipeline sites monitored with satellite imagery in Chicago, 9 (20.5%) show active earthwork or pad expansion, including 5 sites clearing ahead of a reported construction stage.