EndedMoratorium

City of Springfield moratorium

City of Springfield, Missouri paused new data center approvals on 29 Jun 2026 for 4 months, citing zoning and rules and infrastructure. The pause has ended. It covers 2 tracked campuses. Checked 23 Nov 2026

Started 29 Jun 2026EndedEnded 27 Oct 2026

The facts

Term
120 days, through November 17, 2026
Applies to
Exempts projects whose Southwest Power Pool study process had already begun with required fees submitted, and permits council-approved exceptions
Reason
Pause on development, building, site-plan, variance, stormwater, conditional-use, occupancy, public-utility, and large-load electric applications for data centers while the City Manager studies recommendations
Legal basis
Council Bill 2026-147, enacted 2026-06-29 as Ordinance No. 28306 -- although, per a since-filed lawsuit, the ordinance was filed by the City Clerk using resolution-style 'be it resolved' language rather than 'be it ordained,' which the plaintiff argues is itself a charter defect. It imposes a 120-day administrative delay on data center applications/approvals set to expire 2026-11-17.
What happened next
City Council approved Council Bill 2026-147, imposing a 120-day administrative delay on specified data center applications and approvals

Campuses in reach

No tracked campus within 80 km

The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo

Know when City of Springfield votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (2 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near City of Springfield paused data centers?