Data center projects in Missouri
11 campuses are planned or being built in Missouri, with 1.5 GW disclosed so far. 6 have a site permit or later. Checked 27 Nov 2026
11Campuses
1.5 GWDisclosed capacity
18Moratoria in force
MissouriOpen map
One or two campusesThree or more
Project Spade Campus
GoogleMontgomeryAnnounced1,200 MWWildwood Data CenterMP WildwoodJasperSite permit200 MWPatmos Kansas CityPatmos HostingJacksonAnnounced100 MWCentene Data CenterCenteneSt. CharlesSite permitCentene Data CenterCMC RealtySt. CharlesSite permit
OracleCassSite permitGateway Digital Campus
Provident Data CentersFranklinZoningLambda Kansas City
LambdaPlatteAnnouncedOppidan Data Center
OppidanSt. LouisSite permitOracle KC-7/8 Data Centers
OracleCassSite permitProject Green Data Center
AmazonMontgomeryAnnounced
Utility, substation and records for every rowUtility and substationStart Pro · $299/mo
Data center projectNo campuses match
Where Missouri stands
By stage
Top counties
- Cass2
- Montgomery2
- St. Charles2
- Franklin1
- Jackson1
Top owners
OracleNot on record2
Google1,200 MW1- MP Wildwood200 MW1
- Patmos Hosting100 MW1
AmazonNot on record1
Track Missouri in the app, free
Check your email to finish
What the stages mean
- AnnouncedNamed by the owner or an official
- ZoningRezoning filed or approved
- Site permitSite plan or land use approved
- Building permitPermit to build issued
- ConstructionWork on site has started
- OperatingRunning and taking load
Questions
How many data centers are being built in Missouri?
11 campuses are planned or being built. 0 are under construction and 6 have a site permit or later
Announced 4 · Zoning approved 1 · Site permit 6
Which Missouri counties have the most?
How do you know a project is real?
Every campus here is matched to at least one public filing: an announcement, a rezoning, a site plan or a permit. As of 2026-11-27, Wattlas lists 105 campuses in Missouri, 73 of them operating and 21 reported plans not yet confirmed by a filing