Clayton moratorium
Clayton, Ohio paused new data center approvals on 16 Jul 2026 for 12 months, citing zoning and rules. Checked 23 Nov 2026
Started 16 Jul 20264 of 12 months passedEnds 16 Jul 2027
The facts
- Applies to
- None named.
- Term
- 365 days; expires July 16, 2027 unless earlier revoked.
- Reason
- Data centers undefined in Clayton code and could be processed as warehouse uses; concern heightened by the Piqua data center controversy.
- Legal basis
- City of Clayton Resolution No. R-07-26-46 (immediate temporary 365-day moratorium on zoning, conditional use and building permit applications for data processing centers)
- What happened next
- Staff directed to study impacts and prepare zoning text amendments, use classifications and standards for data processing centers.
Campuses in reach
Encore Technologies MSB1Montgomery CountySite permit·≈10–46 MWJ5 Piqua Data CenterMiami CountyAnnounced·1,400 MWCMH01 Holdings LPClark CountySite permit·150 MWConstant CompanyClark CountyAnnounced·ConstantCrusoe Energy SystemsClark CountyAnnounced·CrusoePrologis Butler Data CenterButler CountyZoning·250 MW
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Clayton votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.