In forceMoratorium

Vandalia moratorium

Vandalia, Ohio paused new data center approvals on 20 Apr 2026 for 12 months, citing zoning and rules. Checked 23 Nov 2026

Started 20 Apr 20267 of 12 months passedEnds 20 Apr 2027

The facts

Applies to
None named.
Term
One year (365 days) per council discussion recorded in minutes.
Reason
Council wants time for staff and Planning Commission to develop zoning regulations for data centers; part of a package with discount-store and gas-station moratoria.
Legal basis
City of Vandalia Resolution 26-R-27, temporary moratorium on acceptance, consideration and/or granting of zoning, occupancy or other permits or applications relating to data centers
What happened next
Planning Commission and council to study data center effects and draft zoning regulations.

Know when Vandalia votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Vandalia paused data centers?