Cleveland moratorium
Cleveland, Ohio paused new data center approvals on 15 Jul 2026, citing infrastructure and water use. It covers 23 tracked campuses. Checked 23 Nov 2026
Started 15 Jul 20264 of 7 months passedEnds 29 Jan 2027
The facts
- Applies to
- Review and issuance of specified permit, certificate and license applications for expansion of an existing standalone data center or establishment of a data center as a principal use in a standalone facility; extension adopted October 19, 2026.
- Reason
- Water and power use, outages, low permanent job creation, and zoning/infrastructure review
- Term
- Originally three months from July 20, 2026, subject to earlier regulatory action; extended from October 20, 2026 until the earlier of new or amended regulations or January 29, 2027.
- Legal basis
- Ordinance 556-2026, passed July 15 and effective July 20, 2026; extended by Ordinance 1246-2026, effective October 19, 2026.
- What happened next
- Council adopted a temporary moratorium and extended it by Ordinance 1246-2026; the extension ends on the earlier of qualifying new regulations or January 29, 2027.
Campuses in reach
Progressive InsuranceCuyahoga CountyAnnounced·Progressive InsuranceArk Data Centers Akron 2Summit CountyAnnounced·≈7–34 MWBitdeer NilesTrumbull CountyAnnounced·300 MWBristolville 25 Lordstown Data CenterTrumbull CountyZoning·Bristolville 25 DeveloperStargate LordstownTrumbull CountyConstruction·Oracle
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Cleveland votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (23 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.