Denton moratorium
Denton, Texas has proposed a pause on new data center approvals, citing grid and power and infrastructure. It covers 5 tracked campuses. Checked 23 Nov 2026
The facts
- Term
- Proposed 3 months (per Councilmember Suzi Rumohr's public statement)
- Applies to
- Not specific to a single named project; framed around the cumulative strain of existing and proposed data centers on Denton Municipal Electric's transmission capacity.
- Reason
- grid_energy/infrastructure_capacity: Denton Municipal Electric's transmission system is reported to be operating near capacity, with roughly $300 million in proposed transmission upgrades awaiting an ERCOT response; residents also cited water and community-benefit concerns relative to the roughly $3.5 million in taxes and $9 million in electric ROI/franchise fees existing data centers generate.
- Legal basis
- Not yet adopted; a proposed ordinance following a two-track process (moratorium plus separate development-code amendments) is pending Council hearings.
- What happened next
- Two-track process: separate data-center development-code amendments were adopted October 13, 2026; the proposed 90-day moratorium received its second hearing and first reading October 27, with no action taken at that meeting. Final moratorium adoption remains unverified.
Campuses in reach
Core Scientific Denton Data Center CampusDenton CountySite permit·260 MWData center projectDenton CountyAnnounced·Wells Fargo BankFTW1 DC1 ExpansionDenton CountyBuilding permit·≈35–160 MWACS Fort WorthTarrant CountySite permit·140 MWAligned Dallas DFW03Tarrant CountySite permit·AlignedCyrusOne DFW7Tarrant CountyConstruction·Bosworth Steel Erectors
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Denton votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (5 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.