In forceMoratorium

Fenton Township moratorium

Fenton Township, Michigan paused new data center approvals on 17 Feb 2026, citing zoning and rules and noise. Checked 23 Nov 2026

In force since 17 Feb 2026No end date on record

The facts

Applies to
None identified
Reason
No data-center category in ordinance and resident concern over noise, power, and water
Term
Twelve calendar months; ordinance lists effectiveness February 22, 2026. Exact endpoint convention and later action unresolved.
Legal basis
Charter Township of Fenton Ordinance No. 867, adopted February 17, 2026; publication and effective dates listed February 22, 2026. The document introduction field reads February 3, 2025; prior narrative said 2026
What happened next
Ordinance No. 867 adopted; Planning Commission drafting permanent data center zoning regulations

Know when Fenton Township votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Fenton Township paused data centers?