In forceMoratorium

Hudson moratorium

Hudson, Ohio paused new data center approvals on 14 Jul 2026, citing zoning and rules and grid and power. Checked 23 Nov 2026

In force since 14 Jul 2026No end date on record

The facts

Passed by
City Council, 14 Jul 2026
Applies to
None proposed.
Term
Six months; may be extended another six months
Reason
Preemptive: give staff time to study impacts on the electric grid, water and sewer, telecommunications, noise and tax revenue and recommend zoning standards before any project is proposed.
Legal basis
City Council legislation (six-month stay/moratorium on filing, review and approval of new data center applications), adopted on consent agenda 2026-07-14; legislation number not found
What happened next
Council paused new data center applications for six months while staff study impacts and draft zoning/regulatory standards.

Know when Hudson votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Hudson paused data centers?