Inver Grove Heights moratorium
Inver Grove Heights, Minnesota paused new data center approvals on 26 Jun 2026, citing legal_or_litigation and land use. Checked 23 Nov 2026
In force since 26 Jun 2026No end date on record
The facts
- Passed by
- Inver Grove Heights City Council, 26 Jun 2026
- Applies to
- QLevr LLC's proposed data center (reported as 54,000-55,000 square feet) at 5842 Carmen Avenue East, on the former Travel Tags, Inc. site; anticipated power usage approximately 5 MW/day. This is the specific project the moratorium was adopted alongside in June 2026 and later exempted from it by Ordinance No. 1532 (2026-09-14) after QLevr's lawsuit.
- Reason
- Litigation threat from a data center developer and community opposition; a June 23 meeting reportedly ended in shouting before a scheduled vote
- Term
- One year from the effective date, according to the retained draft; actual publication and effective date have not been established.
- Legal basis
- Ordinance No. 1527, an Interim Ordinance Authorizing a Study and Imposing a Moratorium on Data Centers, adopted by the Inver Grove Heights City Council on 2026-06-26 (3-2) following three readings, under Minn. Stat. Sec. 462.355, subd. 4. Amended by Ordinance No. 1532, adopted 2026-09-14 (3-1), which excludes a single previously submitted Major Site Plan application (the QLevr LLC Carmen Avenue East data center) from the moratorium's application requirements; all other terms of Ordinance No. 1527 remain unchanged.
- What happened next
- One-year moratorium (Ordinance No. 1527) adopted 2026-06-26 on a 3–2 vote following three readings; amendment Ordinance No. 1532 received a final reading on 2026-09-14 to exclude the QLevr application, reportedly on a 3–1 vote, with publication required. Exact effective and end dates and later actions remain unverified.
Campuses in reach
HB Fuller CO - Data Center - Arden HillsRamsey CountySite permit·≈11–52 MWLand-O-LakesRamsey CountyAnnounced·≈39–180 MWSt. Jude MedicalRamsey CountyAnnounced·ST Jude MedicalU.S. Bank N.A. - St. PaulRamsey CountyAnnounced·U S Bank N AWells Fargo Bank N.A. - ShoreviewRamsey CountyAnnounced·Wells Fargo Bank N ABcbsmDakota CountyAnnounced·≈20–93 MW
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Inver Grove Heights votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.