EndedMoratorium

Leavenworth County moratorium

Leavenworth County, Kansas paused new data center approvals on 13 May 2026 for 3 months, citing specific project and noise. The pause has ended. Checked 23 Nov 2026

Started 13 May 2026EndedEnded 10 Aug 2026

The facts

Passed by
Leavenworth County Commission, 13 May 2026
Applies to
Project Bluestem (Cloverleaf Infrastructure), a proposed hyperscale data center south of Tonganoxie, was discussed in connection with the original pause; August 13 reporting said no application had been filed for that project. The later September county resolution recites one data-center application but does not identify it.
Reason
Project Bluestem, a proposed ~600-megawatt (developer statements later cited up to 1.2-gigawatt) hyperscale data center on 1,000+ acres south of Tonganoxie (Cloverleaf Infrastructure/Tailgate Ranch site), drew sustained community opposition (Citizens Against Bluestem) over noise, air quality, health, and infrastructure concerns.
Term
90 days; a later county resolution recites that the original moratorium expired 2026-08-10. The original adoption vote count remains disputed.
Legal basis
Leavenworth County Commission action on May 13, 2026 imposed a 90-day application pause for data centers, battery energy storage systems and cryptocurrency mining, as recited in the later Resolution 2026-16. The original signed instrument and adoption vote count remain unverified.
What happened next
The original 90-day pause expired 2026-08-10 according to a later county resolution. After the failed August extension and vote to revisit a hold, a separate September 2026 resolution provided a data-center pause subject to adoption and publication; its present force remains unverified.

Know when Leavenworth County votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Leavenworth County paused data centers?