Marion County, Florida paused new data center approvals on 15 Sep 2026, citing water use and grid and power. Checked 23 Nov 2026

In force since 15 Sep 2026No end date on record

The facts

Legal basis
Marion County Ordinance No. 26-39, adopted 2026-09-15.
Applies to
An unnamed proposed data-center facility reported by proponents at the hearing as a roughly $10 billion project that could generate about $155 million in tax revenue.
Reason
Concerns over water consumption from the Floridan Aquifer (including Outstanding Florida Springs Silver Springs and Rainbow Springs), power-grid strain, noise, and county staff's stated lack of readiness/criteria to evaluate large data-center applications; balanced against a proposed roughly $10 billion facility that proponents said could generate significant tax revenue and jobs.
Term
Twelve-month moratorium from and including effectiveness, or until earlier qualifying regulations take effect, on accepting or processing applications for data center facilities in unincorporated Marion County, including AI computing and cryptocurrency mining; the ordinance exempts facilities with anticipated monthly peak load under 50 megawatts. A historical report described a standard Special Use Permit process for smaller facilities; that detail remains unverified in the retained original reviewed.
What happened next
12-month moratorium adopted (4-1 substantive vote; 5-0 procedural adoption vote), with exemptions for sub-50-MW facilities that drew a dissenting vote from Commissioner Kathy Bryant, who opposed the carve-out.

Campuses in reach

No tracked campus within 80 km

The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo

Know when Marion County votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Marion County paused data centers?