In forceMoratorium

Martin County moratorium

Martin County, Florida paused new data center approvals on 27 Oct 2026 for 12 months, citing water use and grid and power. It covers 1 tracked campus. Checked 23 Nov 2026

Started 27 Oct 20261 of 12 months passedEnds 27 Oct 2027

The facts

Applies to
WFLX reported that a previously submitted hyperscale data-center application off Kanner Highway would not be affected by the vote; application status and applicable final ordinance provisions remain unverified.
Reason
Water supply, grid infrastructure/rate impacts, air quality, noise, property values ahead of hyperscale project proposals
Term
One year, as reported after the October 27, 2026 vote; Hometown News reported that the ordinance provides 365 calendar days from passage by a majority vote. The enacted instrument, term anchor, exemptions and subsequent actions remain unverified.
Legal basis
Martin County ordinance reported approved on second reading October 27, 2026; ordinance number and official enacted text remain unverified.
What happened next
Direction to staff was followed by two public hearings; news reports describe approval on October 27, 2026 after the second hearing.

Campuses in reach

No tracked campus within 80 km

The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo

Know when Martin County votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (1 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Martin County paused data centers?