In forceMoratorium

Middlefield moratorium

Middlefield, Ohio paused new data center approvals on 9 Jul 2026, citing water use and grid and power. Checked 23 Nov 2026

In force since 9 Jul 2026No end date on record

The facts

Applies to
None named; mayor noted at least one 50-acre parcel in the village.
Reason
Concern about strain on water and power; state legislation (HB 646) stalled.
Term
Twelve months
Legal basis
Village of Middlefield Ordinance 26-136 (emergency), twelve-month moratorium on accepting any zoning application for data centers
What happened next
Village to decide during the 12 months whether to regulate, permit or prohibit data centers; extension possible.

Know when Middlefield votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Middlefield paused data centers?