Montour County moratorium
Montour County, Pennsylvania paused new data center approvals on 18 Nov 2025 for 6 months, citing zoning and rules and land use. The pause has ended. It covers 2 tracked campuses. Checked 23 Nov 2026
Started 18 Nov 2025EndedEnded 17 May 2026
The facts
- Passed by
- Montour County Board of Commissioners, 18 Nov 2025
- Term
- 180 days, expiring about 2026-05-17 unless extended or superseded
- Applies to
- No pending data center applications at enactment; Talen Energy later sought rezoning of Anthony Township parcels for a data-center-related industrial use
- Reason
- Concern over potential data centers or similar large-scale digital/technology facilities; county needed time for Planning Commission ad-hoc committee ordinance work
- Legal basis
- Resolution R-11-19-2025 (the moratorium, now superseded); Ordinance No. 1-2026, the 'Data Center Land Use Ordinance,' enacted by the Montour County Board of Commissioners on April 14, 2026, amending the County Zoning Ordinance to define and regulate Data Centers and Data Center Accessory Uses.
- What happened next
- Following the 2026-02-12 denial of Talen Energy's zoning map amendment, the county completed and enacted the Data Center Land Use Ordinance (Ordinance 1-2026) on 2026-04-14, permitting data centers by conditional use in the Industrial Zoning District rather than prohibiting them outright.
Campuses in reach
5C Data Center Usa Inc.Northumberland CountyAnnounced·5C Data CentersMount Carmel Township Data Center (FIT Energy, near Natalie)Northumberland CountyAnnounced·Fit Energy UsaNautilus Cryptomine LLCColumbia CountyAnnounced·200 MWOutrigger Data Center (Mifflin Township, Columbia County)Columbia CountyAnnounced·Outrigger Industrial AcquisitionsDevil's Mountain (Kline Township, Amazon)Schuylkill CountySite permit·AmazonFrackville Data (KRNL Data Centers)Schuylkill CountyAnnounced·600 MW
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Montour County votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (2 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.