Williamsport, Pennsylvania paused new data center approvals on 25 Jun 2026 for 6 months, citing zoning and rules. It covers 1 tracked campus. Checked 23 Nov 2026
Started 25 Jun 20265 of 6 months passedEnds 22 Dec 2026
The facts
- Applies to
- None; no data center application is pending in the City of Williamsport as of adoption.
- Reason
- Regulatory gap: 1998 zoning ordinance does not account for data centers or their accessory uses; adopted proactively, following similar curative-amendment action by Lycoming County and several county townships, to close the loophole that would otherwise let a developer file a landowner curative amendment and force approval of a data center anywhere in the city.
- Term
- 180 days from adoption to enact a curative amendment under 53 P.S. Section 10609.2, with a follow-up resolution required within 30 days making specific findings of invalidity. Councilman Milliken characterized it as effectively 'hitting pause' on data-center development even though the resolution does not describe itself as a 'pause.'
- Legal basis
- Resolution #10088 (City of Williamsport), adopted June 25, 2026, declaring the city's Zoning Ordinance substantively invalid insofar as it excludes data centers and ancillary buildings or uses, including power generating facilities, and proposing a curative amendment under 53 P.S. Section 10609.2. The July 9, 2026 meeting addressed follow-up Resolution #10091 concerning specific findings.
- What happened next
- Williamsport City Council adopted Resolution #10088 on 2026-06-25, declaring the city's zoning ordinance substantively invalid as to data centers and proposing a curative amendment within 180 days.
Campuses in reach
5C Data Center Usa Inc.Northumberland CountyAnnounced·5C Data CentersMount Carmel Township Data Center (FIT Energy, near Natalie)Northumberland CountyAnnounced·Fit Energy UsaNautilus Cryptomine LLCColumbia CountyAnnounced·200 MWOutrigger Data Center (Mifflin Township, Columbia County)Columbia CountyAnnounced·Outrigger Industrial AcquisitionsSoltier Crypto Data MineBradford CountyAnnounced·SoltierWyalusing Energy Center (Klondike Digital Infrastructure)Bradford CountySite permit·≈140–670 MW
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Williamsport votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (1 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.