Nye County moratorium
Nye County, Nevada paused new data center approvals on 2 Jun 2026, citing water use and grid and power. Checked 23 Nov 2026
In force since 2 Jun 2026No end date on record
The facts
- Passed by
- Board of County Commissioners, 2 Jun 2026
- Legal basis
- Board of County Commissioners resolution under NRS 244.110/244.119
- Applies to
- Manse Technology Campus (formerly 'Project Blackjack'), a proposed ~900-acre, $18.4B Gigawatt Development Partners LLC data center campus in the Pahrump area, is now blocked by the August 18, 2026 Basin 162 ban; per KTNV (2026-09), 'given the ban, it appears to no longer be feasible, at least not where it was originally proposed.'
- Reason
- Nye County Water District Governing Board's 2026-05-27 emergency request that the commission impose a moratorium, driven by concerns over data center water demand on a 'critically over-appropriated' aquifer (Nevada Hydrographic Basin 162) in the Pahrump Regional Planning District
- Term
- No fixed term; Commissioner Strickland was quoted estimating a new data center ordinance could be ready 'in about 90 days,' but the moratorium's stated end condition is adoption of local data center regulations, not a calendar date.
- What happened next
- June reporting describes the June 2, 2026 countywide application moratorium. August 20 reporting describes an August 18, 5–0 Basin 162 ban; the county notice reports Ordinance 631 adoption, conditional publication for effect, while a linked bill suggests potentially broader scope. September 4 reporting says a Bill 2026-14 special meeting was canceled and no replacement hearing was scheduled at that time; its meeting date is internally inconsistent. Final legal scope and later force remain unverified.
Campuses in reach
No tracked campus within 80 km
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Nye County votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.