Data center projects in Nevada

22 campuses are planned or being built in Nevada, with 4.5 GW disclosed so far. 6 have a site permit or later. Checked 27 Nov 2026

22Campuses
4.5 GWDisclosed capacity
3Under construction
5Moratoria in force
Nevada
NevadaOpen map
One or two campusesThree or more

Where Nevada stands

Track Nevada in the app, free

Check your email to finish

What the stages mean

  • AnnouncedNamed by the owner or an official
  • ZoningRezoning filed or approved
  • Site permitSite plan or land use approved
  • Building permitPermit to build issued
  • ConstructionWork on site has started
  • OperatingRunning and taking load

Questions

How many data centers are being built in Nevada?

22 campuses are planned or being built. 3 are under construction and 6 have a site permit or later

Announced 14 · Zoning approved 2 · Site permit 2 · Building permit 1 · Construction 3

Which Nevada counties have the most?
Who is building them?
How do you know a project is real?

Every campus here is matched to at least one public filing: an announcement, a rezoning, a site plan or a permit. As of 2026-11-27, Wattlas lists 119 campuses in Nevada, 60 of them operating and 37 reported plans not yet confirmed by a filing