Plain City moratorium
Plain City, Ohio paused new data center approvals on 10 Aug 2026, citing zoning and rules. It covers 1 tracked campus. Checked 23 Nov 2026
In force since 10 Aug 2026No end date on record
The facts
- Term
- One year; council may extend or remove by legislation
- Reason
- Council-directed preparation of moratorium legislation on new data center applications
- Legal basis
- Ordinance 37-2026, 'Establishing a Temporary Moratorium on Data Center Development Within the Corporate Limits of the Village of Plain City and Declaring an Emergency' (adopted 2026-08-10); does not apply to applications filed before 2026-08-05 or to land already zoned for data center use.
- What happened next
- Council enacted a one-year moratorium (Ord. 37-2026) to research and develop data center zoning regulations.
Campuses in reach
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Plain City votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (1 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.