Ravenna moratorium
Ravenna, Ohio paused new data center approvals on 20 Apr 2026, citing specific project and zoning and rules. Checked 23 Nov 2026
In force since 20 Apr 2026No end date on record
The facts
- Term
- 12 months
- Applies to
- Potential State Route 14/former GE site; existing 500-server bitcoin mining operation reported on property
- Reason
- Property owner interest in a data center at a former GE manufacturing site and gap in zoning code
- Legal basis
- City of Ravenna Ordinance No. 2026-067, adopted April 20, 2026, establishing a one-year temporary moratorium on approval of new data centers; emergency clause adopted.
- What happened next
- Study and drafting of zoning code for data centers, server farms, and cryptocurrency mining facilities
Campuses in reach
Ark Data Centers Akron 2Summit CountyAnnounced·≈7–34 MWBitdeer NilesTrumbull CountyAnnounced·300 MWBristolville 25 Lordstown Data CenterTrumbull CountyZoning·Bristolville 25 DeveloperStargate LordstownTrumbull CountyConstruction·OracleProgressive InsuranceCuyahoga CountyAnnounced·Progressive Insurance
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Ravenna votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.