Rockdale County moratorium
Rockdale County, Georgia paused new data center approvals on 13 Jan 2026, citing zoning and rules. The pause has ended. It covers 4 tracked campuses. Checked 23 Nov 2026
Started 13 Jan 2026EndedEnded 9 Oct 2026
The facts
- Reason
- Allow more time for public input and ordinance revisions
- Term
- Resolution 2026-01 (2026-01-13); extended 2026-05-12 through 2026-09-08; amended by R-2026-24 (2026-08-25) to run through 2026-10-01. Local reporting states the board extended the data-center moratorium through 2026-10-09 on September 22; the adopted extension text and its full scope have not been reviewed.
- Legal basis
- Rockdale County Resolution No. 2026-01 (moratorium on data centers and battery energy storage systems), extended 2026-05-12 and amended by Resolution No. R-2026-24 (adopted 2026-08-25), which exempts the previously approved Treaty Oaks BESS project (FLUM 2025-07 / REZ-2025-13).
- What happened next
- County extended its data center moratorium through 2026-09-08 and held a public town hall the same evening
Campuses in reach
DC BLOX Atlanta EastRockdale CountyConstruction·216 MWMMM Acquisitions Data CenterRockdale CountyAnnounced·MMM AcquisitionsAmazon Data Services Alcovy Road campusNewton CountyAnnounced·≈360–1,600 MWAmazon Data Services, Inc. ATL089 CampusNewton CountySite permit·AmazonBuilding Corner - Amazon Data CenterNewton CountyAnnounced·AmazonSocial Circle Technology ParkNewton CountyAnnounced·SC Infrastructure
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Rockdale County votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (4 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.