DeKalb County, Georgia paused new data center approvals on 25 Jun 2025 for 3 months, citing specific project and zoning and rules. It covers 3 tracked campuses. Checked 23 Nov 2026

Started 25 Jun 202517 of 21 months passedEnds 30 Mar 2027

The facts

Applies to
PCC-DeKalb proposed Ellenwood campus, about 1,000,000 square feet on about 95 acres
Reason
Public health, diesel emissions, water, stormwater, noise, and ratepayer concerns
Term
Initial 100 days; extended multiple times, including June 9, 2026 (100 days, to Sept. 30, 2026) and July 7, 2026 (to March 30, 2027, per Board resolution).
Legal basis
DeKalb County moratorium resolutions, including 2025-12-16 extension (originally numbered draft 2025-1694 per agenda referenced in research notes)
What happened next
County hearing 2026-01-27 on Chapter 27 amendments to define and regulate data centers; permanent ordinance still under development

Know when DeKalb County votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (3 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.