Santa Fe County moratorium
Santa Fe County, New Mexico paused new data center approvals on 30 Jun 2026, citing water use and grid and power. Checked 23 Nov 2026
In force since 30 Jun 2026No end date on record
The facts
- Reason
- Development of permanent standards addressing groundwater, electricity and grid reliability, noise, waste heat, environmental justice, monitoring, and public participation
- Term
- 18 months, immediate; amended during the meeting from an original 12-month proposal
- Legal basis
- Ordinance 2026-06 (Santa Fe County), an immediate 18-month moratorium on data center development, amended at adoption to lower the coverage threshold from 100 MW to 1 MW
Campuses in reach
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Santa Fe County votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.