Westpointe Data Center

A 10 MW data center campus in Albuquerque, New Mexico, built by Clop Albuquerque NM. It has had a site permit since July 2024 and has 4 public records behind it. Checked 27 Nov 2026

Site permitStage since Jul 2024
10 MWCapacity, as stated
4Public records
7Moratoria nearby

How far along

  1. Announced
  2. Zoning
  3. Site permitJul 2024
  4. Building permit
  5. Construction
  6. Operating

The site permit dates from July 2024. A building permit is the next step. Rio Communities has a moratorium in force 45 km away

Bernalillo County, New MexicoParcel, substation and lines

The record

Owner
Clop Albuquerque NM
Stage
Site permit
Capacity
10 MW
Public records
4
Latest record
15 Jun 2026
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
4 records
  • Record 1
  • Record 2
  • Record 3
Utility, substation and 4 public records for Westpointe Data CenterOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Westpointe Data Center?
Clop Albuquerque NM, with Paric also named, according to public records.
How big is it?
10 MW, as stated in a public filing.
Has it been approved?
Yes. It has had a site permit since July 2024.
Is there local opposition?
Yes. 6 moratoria in force and 1 pending nearby.