In forceMoratorium

Santa Rosa County moratorium

Santa Rosa County, Florida paused new data center approvals on 23 Jul 2026, citing zoning and rules. Checked 23 Nov 2026

In force since 23 Jul 2026No end date on record

The facts

Reason
Several residents requested a permanent ban instead of a temporary moratorium.
Term
12-month moratorium on large-scale data centers and large-load-customer facilities in unincorporated Santa Rosa County; permanent rules may be developed sooner than the 12-month endpoint.
Legal basis
The retained county ordinance index identifies Santa Rosa County Ordinance 2026-17 as adopted 2026-07-23 for a large-scale data-center and large-load moratorium. The index also lists similarly titled Ordinance 2026-15 as adopted 2026-07-09; their relationship, signed texts and operative dates remain unverified.

Campuses in reach

No tracked campus within 80 km

The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo

Know when Santa Rosa County votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Santa Rosa County paused data centers?