Starke County moratorium
Starke County, Indiana paused new data center approvals on 15 Dec 2025, citing zoning and rules and infrastructure. The pause has ended. It covers 1 tracked campus. Checked 23 Nov 2026
Started 15 Dec 2025Ended
The facts
- Applies to
- Hyperscale data centers of 5,000 square feet or larger; no named project in captured ordinance
- Reason
- Zoning ordinances lacked hyperscale data center standards; residents raised light, environmental, and infrastructure concerns
- Term
- Original December 15, 2025 moratorium was pending adoption of hyperscale-data-center zoning regulations, with a one-year maximum. The Board adopted the later commercial-data-center prohibition, Ordinance 2026-34, on October 19, 2026; its separate passage/publication effectiveness condition remains distinct from the original adoption trigger.
- Legal basis
- Ordinance 2025-37 imposed the temporary hyperscale-data-center permit moratorium pending zoning adoption. Signed Ordinance 2026-34, adopted October 19, 2026, amends the zoning ordinance to define and prohibit commercial data centers, with specified exclusions and effectiveness after passage and required publication.
- What happened next
- Later adopted zoning imposes a prohibition on defined commercial data centers through Ordinance 2026-34, with specified exclusions; actual publication and present legal effect remain unverified.
Campuses in reach
Lavender Fields Holdings LLC (Michigan City)Laporte CountySite permit·≈63–130 MWMicrosoft Corporation (Mishawaka)Laporte CountyAnnounced·≈390–1,800 MWPhoenix Investments Michigan City Data CenterLaporte CountyAnnounced·Phoenix InvestmentsDigital Egg Investments, LLC (Rochester)Fulton CountyAnnounced·Digital Egg InvestmentsData CenterPorter CountySite permit·≈8–37 MWAmazon Hobart data centerLake CountyAnnounced·≈950–4,400 MW
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Starke County votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (1 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.