Data center projects in Indiana

23 campuses are planned or being built in Indiana, with 1.7 GW disclosed so far. 7 have a site permit or later. Checked 27 Nov 2026

23Campuses
1.7 GWDisclosed capacity
1Under construction
24Moratoria in force
Indiana
IndianaOpen map
One or two campusesThree or more
Meta Lebanon Data CenterMetaBooneConstruction1,000 MWAmazon Hobart data centerAmazonLakeAnnounced≈950–4,400 MWGoogle Morgan County Data CenterGoogleMorganAnnounced390 MWMicrosoft Corporation (Mishawaka)MicrosoftLaporteAnnounced≈390–1,800 MWDigital Crossroads Hammond Campus (DX Hammond)Decennial GroupLakeSite permit200 MW
Utility, substation and records for every rowUtility and substationStart Pro · $299/mo
DC Blox Indianapolis Data CenterDC BloxMarionSite permit78 MWLavender Fields Holdings LLC (Michigan City)Lavender FieldsLaporteSite permit≈63–130 MWData Cave, Inc.Data CaveBartholomewSite permit≈10–46 MWData CenterAmazonPorterSite permit≈8–37 MWAmerican Tower Indianapolis Data CenterAmerican TowerMarionAnnouncedBlocke LLC (Jeffersonville)BlockeClarkAnnouncedDigital Egg Investments, LLC (Peru)Digital Egg InvestmentsMiamiAnnouncedDigital Egg Investments, LLC (Rochester)Digital Egg InvestmentsFultonAnnouncedHatchworks LLC (Ft. Wayne)GoogleAllenAnnouncedJumping Bison Greensburg Data CenterJumping BisonDecaturAnnouncedMetrobloks Indianapolis Data CenterMetrobloksMarionAnnouncedPhoenix Investments Michigan City Data CenterPhoenix InvestmentsLaporteAnnouncedPowerHouse HobartPowerHouseLakeSite permitPrologis Shelbyville Data CenterPrologisShelbyZoningPrologis: Hackman ExpansionPrologisShelbyAnnouncedRadius AllPoints Data CenterRadius Data CentersHendricksAnnouncedSabey Decatur Technology ParkSabeyMarionZoningTerra Industry LLC (Hillsdale)Terra IndustryVermillionAnnounced

Where Indiana stands

Top counties

Top owners

Track Indiana in the app, free

Check your email to finish

What the stages mean

  • AnnouncedNamed by the owner or an official
  • ZoningRezoning filed or approved
  • Site permitSite plan or land use approved
  • Building permitPermit to build issued
  • ConstructionWork on site has started
  • OperatingRunning and taking load

Questions

How many data centers are being built in Indiana?

23 campuses are planned or being built. 1 is under construction and 7 have a site permit or later

Announced 14 · Zoning filed 1 · Zoning approved 1 · Site permit 6 · Construction 1

Which Indiana counties have the most?
Who is building them?
How do you know a project is real?

Every campus here is matched to at least one public filing: an announcement, a rezoning, a site plan or a permit. As of 2026-11-27, Wattlas lists 123 campuses in Indiana, 68 of them operating and 32 reported plans not yet confirmed by a filing