In forceMoratorium

Suffolk moratorium

Suffolk, Virginia paused new data center approvals, citing zoning and rules. Checked 23 Nov 2026

The facts

Passed by
Planning Commission
Reason
City's development ordinance does not mention data centers; warehouse-use rules could be construed to allow them; council wants to avoid being 'blindsided' as happened with solar farms.
Term
WTKR reports a temporary prohibition with no duration specified; the proposed ordinance in the October 21 package specifies no fixed sunset. Final adopted text and current endpoint require verification.
Legal basis
OTA2026-008, recommended by the Planning Commission on 2026-09-15 and presented to City Council on 2026-10-21; WTKR reports approval of a temporary prohibition. The adopted ordinance text and instrument number remain to be verified.
What happened next
WTKR reports unanimous council approval of a temporary prohibition and a halt to data center applications; the final adopted instrument and later status remain unverified.
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo

Know when Suffolk votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.