Data center projects in Virginia

298 campuses are planned or being built in Virginia, with 12.5 GW disclosed so far. 192 have a site permit or later. Checked 27 Nov 2026

298Campuses
12.5 GWDisclosed capacity
34Under construction
5Moratoria in force
Virginia
VirginiaOpen map
One or two campusesThree or more
Hanover Technology ParkTractAshland, VAZoning2,400 MWTract Hanover Technology ParkTractHanoverBuilding permit2,400 MWBroad Run Business Center (EPLAN-2024-0155)Loudoun Technology Partners PropertyLoudounZoning≈1,100–5,000 MWDigital Dulles Land Condo (EPLAN-2024-0060)Digital RealtyLoudounSite permit1,000 MWBull Church Data CenterMid Atlantic State FundCarolineAnnounced≈800–3,700 MW
Utility, substation and records for every rowUtility and substationStart Pro · $299/mo
Upper MagnoliaRosenberger LandChesterfieldZoning≈780–3,600 MWCulpeper Technology CampusPeterson CompaniesCulpeperZoning600 MWAmazon Web Services Louisa County campusesAmazonLouisaSite permit420 MWData center projectVintage Park TwoLoudounZoning≈390–1,800 MWYondr Data CenterYondrLoudounSite permit336 MWINOVA Health System Phase 1 (EPLAN-2023-0051)Beaumeade Crossing 11LoudounSite permit≈320–1,500 MWAmerica Online Technology Center (STPR-2006-0026)American Real Estate PartnersLoudounSite permit300 MWAvaio Digital AppomattoxAVAIOAppomattoxZoning300 MWCarmel Church Data CenterAdp Carmel Church Data HubCarolineSite permit300 MWCrossroads Technology Campus (SUP26-0003)RCK Digital CrossroadsSpotsylvaniaZoning300 MWData center projectChesterfieldSite permit300 MWData center projectMJV AssociatesPrince WilliamAnnounced300 MWData center projectAmazonLoudounConstruction≈300–1,400 MWEdgeCore Dulles Ppa (PBORE-2026-0020)EdgeCoreLoudounZoning300 MWOld Bermuda Data CenterWashington Single Family FundChesterfieldZoning300 MWStack Northern Virginia NVA05 (REZ2023-00026)StackPrince WilliamZoning300 MWTecfusions Clarksville LLCTecfusionsMecklenburgSite permit300 MWWatkins CentreWoodville PartnershipChesterfieldZoning≈280–1,300 MWAshwood AdditionCashvad Ventures LLC PCL 1APrince WilliamSite permit≈270–1,200 MWMerritt I-66 Business Park (REZ1981-0015)I 66 Business Park Industrial OwnerPrince WilliamAnnounced≈270–1,200 MWVWPP Belmont Innovation (PCOR-2023-0016)VantageLoudounZoning≈240–1,100 MWH&M Property (STMP-2020-0016)AmazonLoudounBuilding permit≈220–1,000 MWAstrid (REZ1958-0021)AmazonPrince WilliamConstruction≈210–970 MWProject Nova Southeast Site Plan (PLAT-2024-0185)SDC Ashburn Alpha ILoudounSite permit≈210–960 MWTech Park at Brambleton (STMP-2022-0018)Tech Park at BrambletonLoudounBuilding permit≈210–970 MWDigital Drive Data Center-Trailer CityCoreWeaveChesterfieldSite permit200 MWIron Mountain White Oak Technology Park (RCH1-RCH2-RCH3)Iron MountainHenricoConstruction200 MWManassas Tech Center (REZ2025-00032)Wellington GlenPrince WilliamConstruction200 MWMci Data Center (SPAM-2005-0055)Digital RealtyLoudounSite permit≈200–430 MWCashvad Ventures LLCCashvad VenturesManassasSite permit≈190–410 MWData center projectQuantum ParkLoudounZoning≈190–880 MWLuck Stone Corporation (LEGI-2023-0084)Luck StoneLoudounZoning≈190–860 MWTuscarora Crossing Land Bay 3 (STPL-2020-0046) (PBOND-2024-0128)Tuscarora Landbay 3LoudounZoning≈180–820 MWData center projectGreenlin SR 267LoudounZoning≈170–800 MWOrme Farm RezoningVan Metre Communities LLC Roy BarnettLoudounAnnounced≈170–800 MWAmazon Data Services IAD-870AmazonSpotsylvaniaBuilding permit≈160–350 MWData center projectAmazonSpotsylvaniaBuilding permit≈160–350 MWDigital Loudoun III (SPAM-2016-0109)Digital RealtyLoudounSite permit160 MWGainesville Tech Park Piney Branch (REZ2020-00011)Prince WilliamAnnounced≈160–710 MWRedstone Tech Park North (PLN2008-00253)Prince WilliamAnnounced≈160–720 MWAmazon IAD-667, IAD-668, IAD-669, IAD-670, AND IAD-671Areit Nova ILoudounBuilding permit≈150–310 MWProject Gulfstream (REZ1987-0021)Harry J Parrish Blvd PropertyPrince WilliamAnnounced≈150–710 MWBelmont Landbay KK Data Center (STPL-2023-0025)Belmont Rte 7LoudounZoning≈130–580 MWPacific Corporate Park (EPLAN-2023-0116)Pacific Ashburn CampusLoudounConstruction≈130–280 MWDigital Western Lands LLCDigital Western LandsLoudounSite permit≈120–240 MW

Where Virginia stands

Track Virginia in the app, free

Check your email to finish

What the stages mean

  • AnnouncedNamed by the owner or an official
  • ZoningRezoning filed or approved
  • Site permitSite plan or land use approved
  • Building permitPermit to build issued
  • ConstructionWork on site has started
  • OperatingRunning and taking load

Questions

How many data centers are being built in Virginia?

298 campuses are planned or being built. 34 are under construction and 192 have a site permit or later

Announced 28 · Zoning filed 30 · Zoning approved 48 · Site permit 142 · Building permit 16 · Construction 34

All 298 Virginia pipeline campuses
Which Virginia counties have the most?
Who is building them?
How do you know a project is real?

Every campus here is matched to at least one public filing: an announcement, a rezoning, a site plan or a permit. As of 2026-11-27, Wattlas lists 1,096 campuses in Virginia, 643 of them operating and 155 reported plans not yet confirmed by a filing