Tonawanda moratorium
Tonawanda, New York paused new data center approvals on 3 Aug 2026, citing specific project and environment. It covers 2 tracked campuses. Checked 23 Nov 2026
In force since 3 Aug 2026No end date on record
The facts
- Term
- One year
- Applies to
- Riverview Innovation & Technology Campus's proposed ~300 MW, ~$2 billion data center at the former Tonawanda Coke Corp. site on River Road; as of the vote, the developer said it would continue to review its options with legal counsel.
- Reason
- Specific project: a proposed 300 MW, ~500,000-square-foot, ~$2 billion data center by Riverview Innovation & Technology Campus at the former Tonawanda Coke Corp. industrial site on River Road, which drew sustained resident opposition over environmental, noise, and utility-cost concerns (the site is near the former Love Canal-adjacent area of concern residents cited).
- Legal basis
- Local law imposing a one-year moratorium on data centers of 20 MW or more, Town of Tonawanda, Erie County; signed/filed text not located.
- What happened next
- Town Board unanimously approved a one-year moratorium on new data center applications of 20 MW or more.
Campuses in reach
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Tonawanda votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (2 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.